More drywall from HD.
Along with the drywall, I got a regular 3″ ABS elbow and finished off the vent stack.
After adding vapour barrier to the WC ceiling, I made sure the framing / backing was in for drywall and found that the corner above the shower wasn’t framed as such. I used 2x2s. I dropped one of them down the wall and had to cut another. Oops.
Electrical Code says that a CO smoke detector must be installed in the common area. Why a CO detector is installed up high, I’ll never know. (Carbon monoxide is heavier that air and drops.)
A length of bath ceiling light wiring was switched out to allow for more room between the fixtures.
The ceiling is ready for drywall.
It is complete.
pic to follow
Next, the walls. I had to score the back of this piece along a stud line to fold the sheet. I tried for over an hour to make it fit without folding it without success. In the process, I damaged the left edge and the window area.
Frustrated, I went for a drive and saw this.
I felt somewhat renewed and drove back to do more work.