window insulation; electrical code; kitchen, living room drywall

The can said “low expansion”.  I disagree.  It expanded and dried overnight, and I cut probably 30% of it off.  I’ll know for next time how much to use.  At least it didn’t expand and push the window frame out-of-whack. 

The bedroom and living room new framing gaps were Tuck taped. 

We boarded the west and south walls of the living room and kitchen.  (No pic of the south wall – I’ll get one in the morning.)  In this way, while I’m doing other things, Dave is able to mud and tape these walls. 

After Dave left, I worked on the range outlet (“stove plug”) …

…and added protector plates on the wiring leading to the future water heater. 

 

Floyd and I measured the cutouts for electrical and the kitchen window for the next sheets of drywall, the east wall of the kitchen. 

However, 2×2 backing was needed as you can’t screw drywall to air. 

It was late, and Floyd left.  However, as there was still some daylight left, I added these sheets. 

However, as it was still not dark yet, I removed the non-conforming outlet in the kitchen as required by the electrical inspector. 

Now it’s time to go home.  Next, more drywall sheets.  The main floor mudroom is empty.